Log in


Be aware - extra traffic expected on Bear Creek Road

29 Mar 2022 4:22 PM | Anonymous member (Administrator)

Hi TA!  We have received a notification about some upcoming work on Bear Creek Road (the road that makes up the Three Bears ride) in Lafayette, and thought it best to share with everyone as this is a very popular route for many of us.

East Bay Municipal Utility District’s (EBMUD) plans to remove soil from EBMUD’s storage site at the Briones Reservoir located off Bear Creek Road.  Trucks will be utilizing Bear Creek Road and Camino Pablo to and from Highway 24 for hauling activities.  

The project is planned to begin the week of April 18, 2022, and should last approximately 4.5 months, until late August.  Work hours will be Monday-Friday from 9:00 a.m.-3:00 p.m. during the school year, and 9:00 a.m-4:00 p.m. during the summer break.  

EBMUD says that their project contractor and drivers will be expected to exercise extreme caution while hauling and in the presence of bicyclists and pedestrians. Signs will be posted to alert drivers to bicyclists and alert bicyclists to trucks. Truck drivers will be monitored for compliance with the project’s rules for speed and safety throughout the project.  

However, they are also asking that bicyclists be aware and cautious of trucks during hauling. Bicyclists may choose to plan their trip to avoid that area during the haul times, such as in the early morning, evenings, or on weekends.  

Thanks!


Visit Our Sponsors


Find Us


Instagram announces new changes to the timeline based on feedback -  GSMArena.com news

Contact Us

TeamAlameda
PO Box 1216
Alameda, CA 94501

Powered by Wild Apricot Membership Software